Welcome Guest | Login
Member News Business Alerts Downloads Conferences Calendar Sports Diary
Eskom still pursuing mandatory savings 'safety net'

State-owned power utility Eskom has reiterated its call for South Africans to urgently reduce electricity demand by 10%, or some 3 000 MW, adding that it is continuing to pursue plans to ensure that the energy conservation scheme (ECS) be made mandatory so as to improve savings certainty and enable it to ramp-up planned maintenance.

Providing a power system update in Johannesburg on Monday, CEO Brian Dames said that system would remain constrained for the coming five years, while the maintenance backlog had become unsustainable. Savings were, therefore, needed to create "space" for the utility to implement its proactive maintenance schedule across all of its 58 units.

Eskom was still forecasting a 9 TWh shortfall for 2012, which equated to the operation of a 1 000 MW power station.

Public Enterprises Minister Malusi Gigaba encouraged corporate South Africa, as well as private citizens, to take voluntarily steps to reduce their demand to ensure system stability and to create room for continued economic growth.

But Dames said Eskom required greater certainty on demand reductions and would, thus, continue to pursue a mandatory ECS in its negotiations with business and labour at the National Economic Development and Labour Council, or Nedlac.

These discussions had been under way for a number of years and business had continually raised objections to a mandatory scheme, saying it could result in the curtailment of growth and a reduction in jobs.

Dames stressed that such a compulsory scheme would only be deployed as a last resort “safety net”, while also welcoming the voluntary efforts that had already been made to reduce demand.

However, its top 250 customers had, thus far, only managed to reduce their demand by 1% against a 2007 baseline, even though Eskom's 95 leading industrial customers had achieved average savings of 6.9% against that baseline.

In fact, some mining companies had already breached the 10% savings level and would not be asked to make further mandatory cuts should it be agreed that the ECS be made compulsory.

Overall, Eskom's top customer grouping also included entities, such as the large municipalities, that had not made much progress in reducing demand.

Dames warned that 2012 would be “particularly tight”, owing to the fact that no new major supply would be introduced while demand was still increasing, albeit at a slower rate than initially anticipated.

Demand had returned to 2007 levels, with the summer daily peak of just over 30 000 MW and winter demand likely to peak at above 37 000 MW.

MEDUPI DELAY

Further, the first unit of the coal-fired Medupi power station, which was under construction in Limpopo, would not be introduced during 2012 as initially envisaged. In fact, Dames indicated that the first unit was currently only scheduled to be introduced late in 2013, but that efforts were being made to align the schedule to the first quarter of 2013 schedule outlined in the Integrated Resource Plan, or IRP, for electricity.

In the meantime, much of Eskom's attention had turned to the reliability of the existing fleet, much of which was approaching 30 years.

There was a need to accelerate maintenance efforts at a rate of around 10% of installed capacity during the summer maintenance peak. But owing to the supply constraints, Eskom had been failing to introduce outages as planned and was shifting maintenance out in a bid to keep the lights on. This was increasing the vulnerability of the system to unplanned outages in the longer term and was thus “unsustainable”.

Source - Engineering News

 

<< Back to News

Trade Leads

View Trade leads submitted by your fellow members here. Member login is required.

read more >> MBSA IDC EL IDZ ECDC Life Healthcare First National Battery Real People Eskom Standard Bank Johnson and Johnson
     
Home Services Business News Trade Leads Business Hi-Lite Contact Us Events